Chapter 1. OVERVIEW. ELECTRICAL POWER. Electrical power is an essential element of military operations. Without it, many crucial systems cease to operate. Field Manual (FM) supports engineer, Army, and joint missions throughout full spectrum operations. This FM provides a doctrinal basis for planning. FM The training and experience of prime power NCOs give them an in- depth working knowledge of electrical and electromechanical systems. Each 52E .

Author: Brami Zologore
Country: Congo
Language: English (Spanish)
Genre: Literature
Published (Last): 8 September 2009
Pages: 17
PDF File Size: 17.24 Mb
ePub File Size: 7.65 Mb
ISBN: 165-1-56280-937-6
Downloads: 22471
Price: Free* [*Free Regsitration Required]
Uploader: Grojinn

The mission of engineer prime power units is to generate electrical power and provide advice and technical assistance on all aspects of electrical power and distribution systems in support of military operations. This mission statement encompasses military operations across the entire continuum of military operations to include disaster relief, humanitarian assistance, and other operations short of war.

Engineer prime power units support sustainment engineering efforts by providing reliable power generation and power-related technical expertise. Engineer prime power units can produce large quantities of reliable power with their organic kW generators. They can also install, operate, and maintain nonstandard, portable power-generation equipment and operate and maintain some fixed commercial power plants. The units’ power-generation capability allows them to Each prime power team is equipped with four kW generators, giving the team a 3-MW peak power-production capability.

The team can configure its generators into one large power plant or two smaller plants. Table shows the various possible configurations and the manpower requirements for continuous operation. The team can install and operate these plants in any of three modes.

Chapter 4 contains information on the three modes of power generation. Appendix A contains a discussion of power-generation concepts. The prime power team can install, operate, repair, and maintain nonstandard portable -5422 when they are available.

PDF [Download] Field Manual FM 3-34.480 (FM 5-422) Engineer Prime Power Operations April 2007

Nonstandard generators are nonmilitary, commercial-type generators. Once installed and operational, these generators should be turned over to the supported unit to operate and maintain, thus freeing the prime power team for additional missions. The prime power unit can train the requesting unit personnel to operate and maintain this equipment.

Supported units may use contracting channels to rent or lease these generators. In some cases, nonstandard generators may already be installed as backup. An important consideration when using nonstandard equipment is the availability of service and repair parts.

The prime power team can perform damage assessment of nonstandard power-generation equipment and, subject to availability of repair and service parts, repair the equipment and return it to operation.

Army Regulation AR precludes the purchase of nonmilitary-standard generators without the express approval of the program manager-mobile electric power PM-MEP. Prime power units have a limited capability to operate, maintain, and perform damage assessment of some fixed commercial power plants, especially diesel-engine- and gas-turbine-driven plants.

  AMCRON 2401 PDF

Continuous operation of large fixed plants exceeds the manpower capabilities of the team. In all cases, the prime power team should work with indigenous power-plant operators or contracted technicians who are familiar with the power plant. Prime power unit personnel cannot operate nuclear and fossil-fuel steam-powered plants or hydroelectric plants. In addition to producing power, the prime power unit performs many other technical power-related tasks.

A load survey is an analysis of power requirements. The load survey is a vital preliminary step in providing prime power support. The prime power team conducts a load survey to determine the amount of power a supported unit needs and what the distribution requirements are. The load survey also determines the level of reliability required and identifies any special power requirements or problems.

The recommended power source is determined based on the load survey. A thorough load survey must be completed before work can begin on the installation of a power plant or the design of a distribution system. The prime power team performs analyses of existing distribution networks to determine their capacity and characteristics. This is useful in determining how much power is available on a system and whether the system is expandable or not.

It is also useful in identifying potential electrical hazards that could result in damage to connected equipment, electrocution, or electrical fire. The prime power unit also designs temporary, ground-laid distribution systems. The design includes sizing of conductors, breakers, switches, transformers, load centers, and other devices.

Design calculations include voltage drops as a result of line loss and grounding requirements. The completed design includes circuit diagram and site layout drawings or sketches, a complete bill of materials BOMestimated work requirements, and construction time.

FM Table of Contents

For more complex projects, a critical path method CPM diagram is also produced. Prime power units use these off-the-shelf designs where applicable. AFCS is discussed in Chapter 4. Prime power teams can construct and maintain temporary, ground-laid or buried primary and secondary distribution systems. All distribution systems are designed and constructed with 55-422 material and methods and include appropriate devices. Prime power units have a limited capability to maintain overhead distribution systems.

Construction and maintenance of extensive overhead distribution systems should be accomplished through use of contracts. Prime power personnel can make connections to existing distribution networks. The manpower requirements for construction, maintenance, and repair of nonstandard distribution networks depend on a wide diversity of variables.

Workload estimates for these tasks, which are provided below, are for planning and estimating purposes only and are highly dependent on controlling variables. For planning and estimating purposes, a team can Cm 25 kilometers km of overhead or ground-laid primary distribution line. Maintain 10 km of buried primary distribution line. This is roughly equivalent to the distribution system of a small rural town.

Construct or 5-42 1, 5-42 of ground-laid primary distribution line per day. This includes making in-line cable splices but does not include making connections to distribution transformers. Make 12 connections per day to the primary side of pad-mounted distribution transformers. Make 4 connections per day to the primary side of pole-mounted transformers. Maintain 25 km of overhead or ground-laid secondary 5422 line.

  BERNARDO DE BALBUENA GRANDEZA MEXICANA PDF

Maintain 10 km of buried secondary distribution line.

Construct or repair meters of ground-laid secondary distribution line per day. This includes making in-line splices but fk not include making connections to distribution transformers, load centers, or service equipment.

Make 20 connections per day to service equipment, load centers, and the secondary side of pad-mounted distribution transformers. Make 6 connections per day to the secondary side of pole-mounted transformers. Prime power teams are not normally used to perform interior electrical work such as interior wiring.

This function is performed by the vertical construction platoon of the combat-heavy, engineer-battalion line companies and by engineer utilities detachments. When installing secondary distribution, the prime power team’s responsibilities end at the service entrance. The prime power team is responsible for making the connections to the service equipment.

Service equipment, which is installed by interior electricians, is 5-4222 main distribution panel or switched fuse box inside the structure. The prime power team does conduct a safety inspection of the interior branch circuits and connections before energizing the service equipment. Because the prime power teams have working knowledge of multiple power systems, they are able to repair, maintain, and operate industrial power systems and their associated controls.

These power systems may be encountered in factories or other production plants where large quantities of power are required to operate heavy machinery.

FM Chptr 1 Overview

They may also be encountered in facilities such as ports, fuel-storage complexes, hospitals, refrigeration warehouses, and rail-switching centers. The team can also repair and maintain airfield lighting and other specialized illumination systems. The prime power unit provides power-related technical advice to the appropriate engineer staffs. The prime power unit commander is the theater’s subject-matter expert for electrical power. In this role, he acts as an electrical engineer staff officer to the theater engineer in a mature theater, or to the supported headquarters when a theater engineer is not available, providing information and recommendations on power-related issues.

The prime power unit provides power-related technical assistance to CORs. Prime power personnel can help develop specifications for electrical performance contracts and purchase contracts for electrical material. Performance contracts are needed when a power project exceeds the construction capabilities of the prime power unit or when contracted services are preferred over troop labor.

In addition to developing specifications for contracts, prime power personnel also help perform the technical evaluation of the bids that are received. Sign In Sign Out. Enter Your Email Address.